Parkview Health Core Tower Expansion
A Mold-Tek Technologies Project
2019 SDS/2 Solid Steel Competition | Second Place - Commercial, Small Tonnage
The Challenge The Solution |
Project tonnage Timeline Deliverables |
The Parkview Health Core Tower Expansion in Fort Wayne, IN, presented many detailing challenges for Mold-Tek Technologies, due to complicated geometry and miscellaneous framing for curved brick support, as well as a tight timeline.
The six-story, 168,000 square-foot medical tower allowed the hospital to add 72 inpatient beds and included around 63,000 square feet of shell space for future expansion to support the hospital’s growth forecast.
“We were eager to win this project and reach the next level of craftsmanship on a signature project,” said Amol Gite in Mold-Tek's 2019 SDS/2 Solid Steel Competition submission.
Mold-Tek quoted the project at 4100 hours on a 20-week schedule and felt secure in their ability to get the job done with SDS/2, which they have been using since 2006.
As noted on the Mold-Tek website, “SDS/2 gives our teams the opportunity to continue modeling and detailing through typical connections without waiting on connection design from our customers.”
As the project progressed, they saw a need to add more detailers to the project and ultimately decided to divide the model in two in order to keep everyone moving forward on schedule. While this might have introduced opportunities for error—particularly in managing piecemarks—SDS/2 enabled them to coordinate the two models with minimal effort.
Whereas other detailing software programs require users to manually run commands for a numbering routine, putting them at risk of being out of sync, managing piecemarks is an automated feature in SDS/2. As members are added or changed, marks and quantities for each piece are tracked and updated automatically.
The fabricator, erector, and general contractor all benefited from Mold-Tek’s accuracy and fast turnaround, Gite said. “Erection happened quickly, even though the project was complex.”
“Everything fit up well,” said John Vogt of Ben Hur Construction, the erector on the project.
Ryan Warrick, project manager for Lenex Steel Company, the fabricators on the Parkview project, said Mold-Tek was "quick, responsive, and adhered to all of our detailing standards. Coordination was excellent and drawings were produced on time."
"They are and continue to be the best detailers I have worked with," Warrick said.
Mold-Tek’s work on the project received second place in the Commercial, Small Tonnage category in the 2019 SDS/2 Solid Steel Competition.
Site Photos
Model Photos
Emergency department drive canopy
Miscellaneous brick support and radial framing. Staff entry canopy.
SUBMIT YOUR PROJECT TO THE 2020 SDS/2 SOLID STEEL COMPETITION
This yearly competition recognizes the outstanding work our customers have accomplished using SDS/2 software. The deadline for 2020 content entries is July 31, 2020.
RELATED ARTICLES
Integrated Innovations: A PVS Structures Case Study
PVS Structures is one of the top industrial fabricators in the United States. As technological advancements push the industry forward, they maintain their competitive edge through digitalization and automation, integrating state-of-the-art precision equipment like the Zeman robotic welder with the automated design capabilities of SDS/2’s 3D steel detailing software.
Immersive Art in Denver: A KL&A, Inc. Project
Meow Wolf is a combination of a jungle gym, haunted house, children’s museum, and immersive art exhibit. The project — which was detailed and engineered by KL&A, Inc. — received first place in the Commercial, Large Tonnage category in the 2019 SDS/2 Solid Steel Competition.